Your Energy Logo Home Eco Energy Energy Savings Renewable Energy Your Thoughts News Links

PV Panel

Developing
renewable
energy
programmes

NIE Energy Generation Contract

  1. Introduction

  2. NIE Energy's offer

  3. Why should you choose the NIE Energy Generation Contract?

  4. Who can sign up for NIE Energy Generation Contract?

    You can benefit from this Contract if any of the following apply to you:

    • Your renewable generator is 1MWe or less
    • Your CHP generator is 500kWe or less

    For renewable installations, you must agree to sell NIE Energy both the NIROCs and the export electricity (If applicable).

    1. Export for generators up to 100kW  - Single Rate Export Tariff

      NIE Energy will offer you payment for electricity that you generate but do not use on your premises. This is sometimes referred to as export or spill electricity.

      The current Single Rate Export Tariff offers generators:

      Tariff from 1st October 2009 - 30 September 2010

      Generators up to 100kW

      5.22p/kWh


      This will be paid annually for generators under 10kW or less and generators over 10kW can opt for quarterly or annual payment.

      Import / Export Meter

      NIE Energy requires a simple Import / Export meter to be installed in place of your normal meter. If you require an Import / Export meter and NIE Energy is your supplier then we will arrange this.

      The installation of an Import / Export meter can be requested through the application form, NIE Energy will contact you to arrange this and advise you of the appropriate meter you require and the cost.  For a Single phase meter on a home energy tariff this will be installed free of charge. A quotation for any other meter will be provided on a case by case basis.

      If you require an Import/Export meter to be installed but you are not supplied by NIE Energy you will need to contact your supplier who can arrange for one to be fitted.

      You must have an NIE Grid Connection Agreement in place before an NIE Import / Export meter is fitted. This can be applied for online at www.nie.co.uk/genconnect.

      The meter reader will continue to read your meter and bill you as usual for the amount of electricity that you buy from your supplier. You will be required to read the export element, either quarterly or annually depending on the size of the installation, then submit the reading via e-mail to NIE Energy.

      NIE Energy will then complete a bank transfer for the appropriate amount when we have received and checked your meter reading.

    2. If your generator is between 100kW and 1MW click here.

  5. NIROCs

  6. Feed in Tariff Update

  7. Declarations

  8. Meter readings

  9. Application Process

  10. Correspondence